How Much 500 T/D Tailings Dewatering Screen Cost
Vanadium mine in Shangqiu city the tailings is as high as 500t per day, concentration is 25%, fines
around 100mesh is 70%, using GP tailings dewatering screen can extract 95% dry mine, after
dewatering and screening the tailings water cotent is below 20%. Recycled tailings can be used as
construction materials; water can be recycled, no need to build tailings pond.
A list of the profit:
Processing 2000t/d tailings, after dehydrating, recycled tailings and small content water is aroud
900t, rest 1100t water can be recycled (water price is RMB0.8/t, 1100*0.8=880yuan per day, if runs
for 300 days a year, 880*300=264000yuan=USD44000).
Discharged fines is around 475t per day, RMB10/t, runs for 300 days a year:
475*10*300=1425000yuan=USD237,500
The whole invest of 500t Vanadium mine totaly invest is only around RMB500,000 =USD83,300